GSK Monitoring system project in Lactam and Non lactam building, For 60 room of the manufacturing zones, the project was monitoring for temperature & humidity and differential pressure between rooms with multichannel flush mounted display in zone to monitor the three parameters and allow for visual and audible alarm if the measured parameter increase above or decrease below the desired set point as per customer requirements, the displays is comply with clean room requirements.

Project Details

The project scope is to install, commission, program and hand over the sensors located in the clean room area to EMS Schneider Ecostruxure building operation software and make all GUI that make clients apple to monitor the readings, charts, history, tables, alarms, audit trails, user management and other features.
The reference that project comply with is CFR21 part11 which make sure the data integrity and security levels, also from our scope was BMS validation that contain IQ, OQ tests that was implemented by our team and audited and approved by validation and Quality GSK team.